Flashing: The flashing configuration will depend on the surrounding construction. You can install the flashing before or after the new window (Method A or B) is placed in the rough opening. Either way, the flashing must be installed in a manner to preclude entry of water into the wall cavity and the rough opening gap. In some cases, the window may have an integral flashing design. In other cases, flashing materials can be used in conjunction with the application of the finish siding. (See section on Penetration Flashing) Header Drip Cap: At the head of the window, a drip cap should be installed from under the sheathing paper at the header, to beyond the exterior face of the window. It should also extend past the trim at the sides of the window. Install a continuous piece of aluminum or galvanized flashing material onto the building sheathing, tucked under the sheathing paper, with a 90 degree bend to extend over the new window’s header. A 1/4” return bend is applied down the face of the window’s header. To finish, the siding veneer will overlap the header flashing. Penetration Flashing: Material for flashing shall be barrier coated reinforced flashing material and shall provide for 4-hour minimum protection from water penetration when tested in accordance with current ASTM specs. Drip Cap, Penetration Flashing Basics WINDOW BRICK MOULD TRIM CAULK GAP BRICK VENEER Window Fitters Guide to Window Installation 18 ©2022 AWDI, LLC Do not reproduce without permission Sealant used with penetration flashing techniques shall comply with current Federal Specifications. Application: To flash against water penetration in a wood frame and sheathing application, a strip of approved flashing material, at least 9” wide, shall be applied in overlapping, weatherboard fashion (counter flashing), on all sides of the opening. The first strip is applied horizontally immediately underneath the sill - before the window is installed. It should be long enough to extend past each side of the window, and beyond the jamb flashing when it is applied. Fasten the top edge of the sill flashing to the sill, but do not secure the middle or lower edge so that building paper, later applied, may be slipped up and underneath the bottom of the applied sill flashing. Next cut and apply the two vertical jamb flashing seg- ments, again making them 9 inches wide, and suffi- ciently long enough to extend above the (to be applied) header flashing, and to extend below the (already applied) sill flashing. The jamb flashings should overlap the applied sill flashing. Fasten only the top portion of the jamb flashing so that the lower section(s) will allow the to be applied building paper to be slipped up and underneath the jamb flashing ends as well as the sill flashing. Header Flashing Overlaps Jamb Flashing Window Installed With Fin Sill Flashing Jamb Flashing Building Paper Applied Over Sheathing Window Frame Jamb and Sill Flashing Overlaps Building Paper SAMPLE MANUAL
View this content as a flipbook by clicking here.